What happens automatically in Purchasing

Use this as a checklist when deciding whether a save has completed the business process.

Your actionWhat changes automaticallyWhat still needs a person
Save orderCalculates line/header/base amounts and saves DraftReview the total, supplier and terms; Submit.
SubmitRevalidates supplier/references, evaluates approval, records pending/approved decisionIndependent approval when required; supplier communication.
ApproveRecords actor, time, decision and revision contextIssue/acknowledgement where applicable.
Issue / AcknowledgeRecords workflow state and referenceActual external communication.
AmendSaves revision history and re-evaluates commercial approvalReview the resulting state and re-issue if needed.
Save draft receiptStores the draftReview then Post receipt; no stock change yet.
Post receiptUpdates received/accepted/rejected totals and dispatches accepted stock additionVerify the correct Inventory movement and resolve integration problems.
Create draft invoiceUses accepted quantities; advances PO invoiced progress; may close POCheck against supplier bill, then Post invoice.
Post invoiceRecords Posted and sends the liability event to AccountingRecord the actual payment and allocate it.
Post paymentSaves a Posted payment, initially unallocatedAllocate it to the correct invoice(s).
Allocate paymentUpdates payment availability and invoice paid/due/status; sends the accounting eventReconcile against payment evidence and supplier statements.
Close/cancel a lineRecords reason, actor and control/quantity change; recalculates operational stateResolve physical/financial exceptions separately.

Numbering​

The browser requires PO number and Receipt number on creation. Purchase invoice and vendor payment numbers are generated. The supplier's invoice number is entered separately. Record numeric IDs too, because the invoice/payment lookup screens use them.

No stock change at order approval​

Purchase orders do not reserve or add inventory when submitted/approved. The stock addition is associated with a posted receipt's accepted quantity. Posting an invoice or allocating payment does not add the goods a second time.

The Inventory step follows receipt commit and requires the right references. See setup limitations and verification.

Completion and payment are independent​

A Closed PO does not prove a posted or paid invoice. An Allocated payment proves the recorded allocation, not bank settlement. Review each document's own status.

Things you should not expect automatically​

  • No supplier email, bank transfer, bank export or settlement confirmation.
  • No supplier returns/debit-note workflow or posted-receipt reversal in these screens.
  • No complete inspection, lot or serial workflow from Inspection required.
  • No automatic prorating of PO line tax/discount to partial receipts, or automatic inclusion of header charges in generated invoices.
  • No automatic replacement order for rejected goods.
  • No editable invoice-matching exception queue or automatic decision that a bill discrepancy is acceptable.
  • No automatic refresh of agreed historical supplier information after a master-data change.